Question 81

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

A. Quote
B. Information
C. Proposal
D. Bid
Show Answer
Correct Answer: C
Explanation:
A proposal is requested when the buyer seeks a vendor's detailed technical and management approach, solution, and commercial terms for a complex service where factors beyond price matter. Quotes are for standard items, bids are typically for well-defined procurements often awarded primarily on price, and information requests are for market research rather than selecting a solution.

Question 82

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

A. Executing the approved contingency plan
B. Constructing an Ishikawa diagram to determine the root cause
C. Using a Pareto chart to prioritize the different causes
D. Engaging the senior management team in regard to the issue
Show Answer
Correct Answer: B
Explanation:
The team is performing root cause analysis by gathering perspectives to understand why the documentation quality was poor. An Ishikawa (fishbone/cause-and-effect) diagram is a standard quality management tool used to organize and analyze potential causes. The other options describe contingency execution, prioritization of causes (Pareto), or escalation to senior management, none of which match the activity described.

Question 83

A project manager is meeting with business stakeholders to define the time frame for a go live to occur without impacting business operations. Which of the following is the project manager working on?

A. Validation check
B. Downtime window schedule
C. Customer notifications
D. Risk analysis
Show Answer
Correct Answer: B
Explanation:
Defining the time frame for a go-live that avoids disrupting business operations is planning the deployment's scheduled downtime window. This focuses on selecting an appropriate maintenance window rather than validating the system, notifying customers, or performing risk analysis.

Question 84

Which of the following best describes why conducting lessons learned sessions is important?

A. To discuss as a team how to improve and eliminate all the issues in the project
B. To conduct the team’s performance evaluation and document the results
C. To report all the mistakes and ensure others do not make the same ones
D. To document what went right and wrong, as well as possible improvements
Show Answer
Correct Answer: D
Explanation:
Lessons learned sessions are intended to capture and document both successes and failures, along with recommendations for improvement, so that future projects can benefit from the experience. They are not primarily for performance evaluations, assigning blame, or eliminating all issues in the current project.

Question 85

The development phase of a project is coming to an end, and the product is ready. The project manager needs to develop a transition/release plan to ensure a smooth launch. Which of the following activities should be included in the plan?

A. Preliminary needs assessment
B. Work breakdown structure
C. Operational handoff
D. Budget reconciliation
Show Answer
Correct Answer: C
Explanation:
A transition/release plan is intended to move the completed product from the project into operational use. A key activity is the operational handoff, including transferring responsibility, documentation, support processes, and readiness to the operations team. The other options are project planning or closing activities rather than core elements of a transition/release plan.

Question 86

Which of the following is a characteristic that defines a project?

A. Will produce a profit
B. Uses outside resources
C. Requires a well-defined scope
D. Has a defined start and finish
Show Answer
Correct Answer: D
Explanation:
A project is defined as a temporary endeavor undertaken to create a unique product, service, or result. A defining characteristic is that it has a definite beginning and end. Profit is not required, outside resources are not required, and while scope should be defined for effective management, having a well-defined scope is not the defining characteristic of a project.

Question 87

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

A. Issue log
B. Risk register
C. Defect log
D. Traceability matrix
Show Answer
Correct Answer: D
Explanation:
A requirements traceability matrix maps requirements to their origin, implementation, and verification. It allows the project manager to trace a problematic item back to the stakeholder or source that requested it. The issue log tracks issues, the risk register tracks risks, and the defect log records defects but not the original requester.

Question 88

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

A. Resource management system
B. Issue log
C. Ticketing system
D. Backlog
Show Answer
Correct Answer: D
Explanation:
A backlog is the prioritized list of work items, features, or deliverables that remain to be completed, making it the appropriate tool for tracking outstanding complex deliverables. A resource management system tracks people and capacity, an issue log tracks problems, and a ticketing system is generally for service/support requests rather than overall project deliverables.

Question 89

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

A. Update the WBS.
B. Escalate to the CC
C. Accept the change.
D. Implement the change.
Show Answer
Correct Answer: B
Explanation:
A change request that will affect the project baseline (schedule and budget) should be evaluated through integrated change control. The project manager should submit/escalate it to the Change Control Board (CCB) or the organization's change control process for review and approval before updating planning documents or implementing the change. Updating the WBS or implementing/accepting the change comes only after approval.

Question 90

Which of the following is a quantitative key performance indicator?

A. The project sponsor ranked the graphics of an application as four out of five.
B. The project implements the application in ten different geographical regions.
C. The workers complete tasks on average 25% faster using a new application.
D. The use of a multimedia interface appeals more to users under the age of 21.
Show Answer
Correct Answer: C
Explanation:
A quantitative KPI is expressed as a measurable numeric performance metric. Option C measures productivity improvement as an average of 25% faster task completion, making it a true quantitative KPI. Option A is a subjective rating, B is a deployment scope/count rather than a performance indicator, and D is a qualitative statement about user preference.

$19

Get all 383 questions with detailed answers and explanations

  • Instant download HTML + PDF delivered the moment payment clears.
  • Secure Stripe checkout we never see or store your card details.
  • 7-day refund if files are defective see our refund policy.