Comptia

PK0-005 Free Practice Questions — Page 16

Question 151

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

A. IaaS
B. XaaS
C. PaaS
D. SaaS
Show Answer
Correct Answer: D
Explanation:
SaaS is the best fit because it provides a centrally hosted, ready-to-use application that can unify operations across global franchise locations while enabling real-time, centralized reporting without relying on local managers to generate or submit reports. IaaS and PaaS provide infrastructure or application development platforms rather than a complete business application, and XaaS is a broad umbrella term rather than a specific deployment model.

Question 152

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take NEXT?

A. Inform the CCB to stop communication.
B. Establish a RACI matrix.
C. Escalate the communication issues.
D. Revise the communication plan.
Show Answer
Correct Answer: D
Explanation:
The stakeholder's concern indicates the project's communications are not meeting stakeholder needs. The appropriate next step is to update the communications management plan to adjust communication methods, frequency, or recipients. Informing the CCB is unrelated, a RACI matrix defines roles rather than communication preferences, and escalation is unnecessary before attempting to resolve the issue through the communication plan.

Question 153

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A. Escalate to vendor management.
B. Consult the request for proposal.
C. Review the meeting cadence.
D. Reinforce the rules of engagement.
Show Answer
Correct Answer: D
Explanation:
The project manager should address the immediate governance issue by reinforcing the agreed rules of engagement, including meeting participation expectations and access. Escalating to vendor management is unnecessary unless the issue persists or is intentional. The request for proposal is unrelated to meeting attendance, and reviewing meeting cadence does not address the underlying access/protocol problem.

Question 154

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do NEXT?

A. Obtain details from the owner of the project.
B. Update the critical path for the project.
C. Apply contingency reserves.
D. Reestimate epic user stories.
Show Answer
Correct Answer: A
Explanation:
The appropriate next step is to gather information from the project owner/project manager to understand the nature, cause, duration, and impact of the delayed deliverables before deciding on corrective actions. Updating schedules, using contingency reserves, or reestimating work would be premature without first assessing the situation.

Question 155

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do NEXT?

A. Request a change control ticket.
B. Review the schedule plan.
C. Refine the project documentation.
D. Revise the communication plan.
Show Answer
Correct Answer: D
Explanation:
The deliverable was completed and provided on time, so the schedule and scope are not the issue. The escalation occurred because the external group did not know the deliverable was available, indicating a breakdown in stakeholder communication. The next appropriate action is to revise the communication plan so the right stakeholders are informed through appropriate channels and timing. A change request is unnecessary, reviewing the schedule does not address the root cause, and refining documentation alone does not fix the communication process.

Question 156

A popular application that has been used by clients everywhere is prohibited in one particular jurisdiction because of security concerns. Which of the following should a project manager do?

A. Conduct an analysis to find a comparable application that is allowed in the particular jurisdiction.
B. Continue implementing the existing application because it is proven to be secure elsewhere.
C. Build a new application in house that is comparable to the existing application.
D. Cancel the project and begin project closeout activities.
Show Answer
Correct Answer: A
Explanation:
A project manager should ensure the solution complies with applicable laws and regulations. If a commonly used application is prohibited in a jurisdiction, the appropriate response is to evaluate and select a compliant alternative. Continuing with the banned application violates regulatory constraints, building a new application is a costly option without first assessing available compliant alternatives, and canceling the project is premature if viable alternatives exist.

Question 157

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A. Start-to-finish
B. Finish-to-finish
C. Finish-to-start
D. Start-to-start
Show Answer
Correct Answer: C
Explanation:
Testing is not allowed to start until the requirements development activity has finished. This is a classic Finish-to-Start (FS) dependency, where the successor activity (testing) starts only after the predecessor activity (requirements development) finishes.

Question 158

A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

A. Avoid
B. Transfer
C. Accept
D. Share
Show Answer
Correct Answer: B
Explanation:
Outsourcing work to an external vendor shifts responsibility for certain risks associated with delivering that work to a third party through a contract. This is a risk transfer response, commonly used when specialized expertise or resources are lacking. While both parties may still retain some risks, the primary risk response demonstrated is transfer.

Question 159

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update NEXT?

A. Schedule
B. Status report
C. Issue log
D. Task board
Show Answer
Correct Answer: C
Explanation:
The legal department's rejection means the identified risk has occurred and is now an active issue. After triggering the planned risk response, the next project document to update is the issue log so the issue can be tracked, assigned, and managed. The schedule may later require updates if impacts are confirmed, and the status report will communicate the situation in the next reporting cycle, but the issue log is the immediate record for a realized problem.

Question 160

Project team members have questions regarding their responsibilities during the latest sprint. Which of the following personnel would MOST likely be able to assist?

A. Product owner
B. Team leader
C. Product manager
D. Scrum master
Show Answer
Correct Answer: D
Explanation:
The Scrum Master is responsible for ensuring the Scrum framework is understood and followed, coaching the team, facilitating ceremonies, and helping clarify roles, responsibilities, and process issues during a sprint. The Product Owner manages the product backlog and priorities, the Product Manager focuses on broader product strategy, and 'Team leader' is not a defined Scrum role.

$19

Get all 383 questions with detailed answers and explanations

  • Instant download HTML + PDF delivered the moment payment clears.
  • Secure Stripe checkout we never see or store your card details.
  • 7-day refund if files are defective see our refund policy.