Question 161

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A. The project manager did not release the resources.
B. The project is in the verification testing phase.
C. The project manager did not complete the project closure phase.
D. The project manager did not remove access.
Show Answer
Correct Answer: C
Explanation:
A successful production release does not by itself mean the project is formally complete. If the project manager continues to receive project-related work, the most likely cause is that formal project closure was not completed, leaving administrative tasks, handoffs, documentation, lessons learned, and final acceptance unresolved. The other options do not generally explain ongoing project work after production release.

Question 162

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

A. Rational Unified Process
B. Waterfall
C. Agile
D. DevOps
Show Answer
Correct Answer: C
Explanation:
Agile is designed for situations where requirements are evolving or not well defined. It uses iterative development to deliver a minimum viable product (MVP), gather feedback, and refine the product over successive iterations. Waterfall and Rational Unified Process are generally more plan-driven, and DevOps focuses on software delivery and operations rather than requirements discovery or project delivery methodology.

Question 163

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

A. Use a software tool during the meeting that can create a transcript of what is discussed.
B. Have a standing agenda that is vague enough so that it can be used again.
C. Delegate the roles and responsibilities to improve meeting management.
D. Reprimand project team members for not completing assigned action items.
Show Answer
Correct Answer: C
Explanation:
Delegating meeting roles (such as note-taking, timekeeping, and action-item tracking) increases shared ownership and accountability, allowing the project manager to focus on facilitation and follow-up. This helps improve meeting management and reinforces responsibility for completing action items. The other options either do not address accountability (A, B) or are unnecessarily punitive (D).

Question 164

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the MOST important prerequisites? (Choose two.)

A. Rollback plans
B. Project management plan
C. Deployment plan
D. Asset management plan
E. Communication plan
F. Resource management plan
Show Answer
Correct Answer: A, C
Explanation:
Before implementing a production infrastructure change, the key operational prerequisites are a deployment plan that defines how the change will be executed and a rollback plan that defines how to restore service if the implementation fails. Communication is important, but it is typically part of the change process rather than the two most critical implementation prerequisites.

Question 165

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

A. Telephone
B. Videoconference
C. Face-to-face
D. Email
Show Answer
Correct Answer: D
Explanation:
Email is a push communication method: the sender distributes information to recipients, but there is no assurance it has been received, read, or understood. Telephone, videoconference, and face-to-face communication are interactive methods that provide immediate feedback and greater assurance of receipt.

Question 166

A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?

A. Too much time might be spent generating project delays.
B. The project manager might be seen as weak.
C. The number of change requests throughout the project might be reduced.
D. Some stakeholders might not be completely satisfied.
Show Answer
Correct Answer: D
Explanation:
The scenario describes the compromise (reconcile) conflict resolution technique, where each stakeholder gives up something to reach an acceptable solution. The typical outcome is that no party is fully satisfied, even though agreement is reached. This does not inherently reduce change requests, nor does it imply weakness or excessive delays.

Question 167

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following would most likely take place during a Scrum ceremony?

A. Reviewing project blockers
B. Defining roles and responsibilities
C. Establishing a project schedule
D. Determining a project budget
Show Answer
Correct Answer: A
Explanation:
Scrum ceremonies include Sprint Planning, the Daily Scrum, Sprint Review, and Sprint Retrospective. During the Daily Scrum, the team discusses progress and identifies impediments or blockers that need to be addressed. Defining roles and responsibilities, establishing the overall project schedule, and determining the project budget are project management activities, not typical Scrum ceremony activities.

Question 168

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A. Change the precedence of the tasks to “finish-to-start”.
B. Evaluate and modify the schedule with a burndown chart.
C. Assign additional resources to prevent overwork.
D. Perform critical path analysis.
Show Answer
Correct Answer: A
Explanation:
The overload is caused by one resource being assigned multiple concurrent tasks. Since the tasks can be executed independently, the appropriate scheduling adjustment is to remove the unnecessary parallelism for that resource by changing the relationship to finish-to-start (or otherwise sequencing the work). Assigning additional resources is a possible response but is not the first scheduling correction when the issue is caused by task logic and resource allocation. A burndown chart is not used to modify schedules, and critical path analysis identifies schedule drivers rather than resolving a resource overallocation.

Question 169

A project team wants to compare two potential vendors’ costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

A. Scatter diagram
B. Decision tree
C. Pareto chart
D. Histogram
Show Answer
Correct Answer: B
Explanation:
A decision tree is the appropriate visualization for comparing alternative vendors by modeling decision paths, costs, risks, probabilities, and expected outcomes. Scatter diagrams show relationships between variables, Pareto charts prioritize categories by frequency or impact, and histograms display data distributions rather than decision alternatives.

Question 170

During the execution phase of a project, the project team faced an unexpected website downtime. The project manager held a brainstorming session, and the team identified causes and effects for the problem. Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A.
B.
C.
D.
Show Answer
Correct Answer: B
Explanation:
A scatter diagram (scatter chart) is used to analyze whether two variables are correlated, helping determine whether a suspected cause and effect relationship exists. After identifying possible causes through brainstorming, the team can use a scatter diagram to evaluate the relationship between a particular cause and its effect.

$19

Get all 383 questions with detailed answers and explanations

  • Instant download HTML + PDF delivered the moment payment clears.
  • Secure Stripe checkout we never see or store your card details.
  • 7-day refund if files are defective see our refund policy.