In which of the following types of architectures is an application moved from Dev to QA to Test to Production?
A. Tiered
B. Business
C. Process
D. Governance
Show Answer
Correct Answer: A
Explanation: Moving an application through Dev, QA, Test, and Production refers to distinct deployment environments (tiers) in the software lifecycle. This aligns with a tiered/environment-based architecture, not business, process, or governance architectures, which describe organizational logic, workflows, or oversight rather than deployment stages.
Question 63
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
A. Concept of operations
B. WBS
C. Integrated master schedule
D. RACI
Show Answer
Correct Answer: D
Explanation: A RACI matrix explicitly defines who is Responsible, Accountable, Consulted, and Informed, which directly identifies who to communicate with and at what level. The other artifacts do not focus on communication roles.
Question 64
During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?
A. Work breakdown structure
B. Change log
C. Project success criteria
D. Milestone chart
Show Answer
Correct Answer: C
Explanation: During project initiation, the focus is on defining what success looks like for the project. Project success criteria clearly specify the goals, required deliverables, and measurable constraints such as cost and time that must be met for the project to be considered successful. The other options are tools used later or for different purposes (WBS for scope decomposition, change log for tracking changes, milestone chart for scheduling), not for defining success criteria.
Question 65
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
A. Some work packages are missing from the WBS.
B. Information is missing from the RACI matrix.
C. New knowledge bases were introduced.
D. Team touch points are missing.
Show Answer
Correct Answer: B
Explanation: Disagreements about assigned tasks during execution usually stem from unclear roles and responsibilities. The RACI matrix is specifically designed to define who is Responsible, Accountable, Consulted, and Informed for each task. Missing or incomplete information in the RACI leads to confusion over ownership and accountability, causing team members to disagree about their assignments.
Question 66
Which of the following statements best represents a network issue?
A. The development team on the fourth floor is unable to access servers and email services.
B. Cell phones served by a specific telecom company are getting a “no service” message.
C. A user cannot connect to Wi-Fi because of a wrong ID or password.
D. A user is receiving an automatic reply message saying that an email address does not exist.
Show Answer
Correct Answer: A
Explanation: A network issue typically affects connectivity to shared network resources within a specific area. The inability of an entire team on one floor to access servers and email indicates a localized network connectivity problem. The other options involve telecom provider outages, authentication errors, or email address issues, which are not core network issues.
Question 67
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?
A. Define access requirements.
B. Develop a transition plan.
C. Create a responsibility assignment matrix.
D. Create a work breakdown structure.
Show Answer
Correct Answer: A
Explanation: Controlling who can modify project documents and artifacts requires defining permissions and restrictions. Defining access requirements establishes who can view, edit, or approve data, which directly addresses document and data control. The other options focus on planning, roles, or scope decomposition rather than access control.
Question 68
A project manager provided details regarding the completion of the following tasks:
• Vendor selection took less time than planned.
• Equipment procurement took less time than estimated.
• Equipment installation went according to schedule.
Which of the following should the project manager update?
A. Change log
B. Project Gantt
C. issue log
D. Requirements traceability matrix
Show Answer
Correct Answer: B
Explanation: The information describes actual schedule performance: two tasks finished earlier than planned and one finished on time. This requires updating the project schedule to reflect actual durations and progress. The Gantt chart is the schedule model used to track and update task timing. A change log is for approved changes, an issue log is for problems, and the requirements traceability matrix tracks requirements, not schedule performance.
Question 69
A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?
A. Resolution time
B. Issue list
C. Work breakdown structure
D. Cost optimization
Show Answer
Correct Answer: A
Explanation: A Service Level Agreement (SLA) defines measurable service performance commitments, such as response and resolution times for incidents. Items like an issue list, work breakdown structure, or cost optimization are not core SLA elements.
Question 70
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
A. Statement of work
B. Business case
C. Requirements document
D. Work breakdown structure
Show Answer
Correct Answer: B
Explanation: During project initiation, the business case documents the business justification, reasons, expected benefits, and value of the project and is used to obtain approval. The other options serve different purposes (SOW defines scope/deliverables, requirements detail needs, WBS decomposes work).
Question 71
Which of the following would be best to utilize when managing communications for project teams across multiple time zones?
A. Business collaboration tool
B. Email
C. Virtual meetings
D. Enterprise CMS
Show Answer
Correct Answer: A
Explanation: A business collaboration tool is best for managing communications across multiple time zones because it supports asynchronous messaging, shared workspaces, file sharing, and task coordination without requiring team members to be online simultaneously. Email is slower and fragmented, virtual meetings are difficult to schedule across time zones, and an enterprise CMS is designed for content management rather than team communication.
$19
Get all 377 questions with detailed answers and explanations
Instant download HTML + PDF delivered the moment payment clears.
Secure Stripe checkout we never see or store your card details.
7-day refund if files are defective see our refund policy.