Question 51

A project came in under budget, so the senior management team celebrated by spending the unused budget on shirts for team members and a cake for the entire company. In which of the following project phases did this take place?

A. Planning
B. Closing
C. Execution
D. Initiation
Show Answer
Correct Answer: B
Explanation:
Celebrating project completion, recognizing the team, and disposing of or using remaining project funds are activities associated with the Closing phase. The statement that the project came in under budget implies the work has been completed and is being closed out.

Question 52

Which of the following best describes Kanban in the context of project management?

A. A visual management system for tracking work progress
B. A document management tool for project artifacts
C. A decision-making technique for risk management
D. A scheduling tool for Gantt charts
Show Answer
Correct Answer: A
Explanation:
Kanban is a visual workflow management method used to visualize work, limit work in progress, and track the progress of tasks through different stages. It is not primarily a document management tool, risk decision technique, or Gantt chart scheduling tool.

Question 53

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in network that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A. 9 days and $3,000
B. 10 days and $3,200
C. 12 days and $3,800
D. 13 days and $3,600
Show Answer
Correct Answer: B
Explanation:
Use expected monetary value and expected schedule impact for budgeting contingency based on the 20% risk probability. Expected schedule contingency = 5 days × 0.20 = 1 day, so budget 9 + 1 = 10 days. Expected cost contingency = $1,000 × 0.20 = $200, so budget $3,000 + $200 = $3,200.

Question 54

A project manager has determined that the critical path of a project is 243 days. However, knowing that the standard deviation is eight days, the project manager would like to provide an estimate to the stakeholders with 95% confidence. Which of the following time frames should the project manager communicate to the stakeholders?

A. 195-291 days
B. 219-267 days
C. 227-259 days
D. 235-251 days
Show Answer
Correct Answer: C
Explanation:
For a normally distributed PERT estimate, a 95% confidence interval is approximately the mean ± 2 standard deviations (more precisely ±1.96σ). With a mean (critical path) of 243 days and σ = 8 days, the interval is 243 ± 16 ≈ 227 to 259 days (or 243 ± 15.68 = 227.32 to 258.68, rounded). This matches option C.

Question 55

Which of the following would be considered a CapEx budget item?

A. Smoke testing
B. Adding new functionality
C. Writing code to fix a bug
D. Hiring a new developer
Show Answer
Correct Answer: B
Explanation:
Capital expenditures (CapEx) are costs that create or significantly enhance a long-term asset. Adding new functionality that extends or improves software beyond routine maintenance is typically capitalizable. Smoke testing, bug fixes, and hiring a developer are generally operational expenses (OpEx), with salaries only potentially capitalizable under specific accounting rules, but hiring itself is not a CapEx item.

Question 56

Which of the following is the best example of CapEx?

A. Taxes
B. Vehicles
C. Salaries
D. Utilities
Show Answer
Correct Answer: B
Explanation:
Capital expenditures (CapEx) are investments in long-term assets that provide benefits over multiple accounting periods. Vehicles are tangible fixed assets typically purchased as CapEx, whereas taxes, salaries, and utilities are operating expenses (OpEx).

Question 57

Which of the following best describes why a SaaS application might be used to provide a multiplatform service to a project management team?

A. The SaaS application would provide additional computing resources if needed by team members to complete tasks.
B. The SaaS application would allow users to access a virtual desktop from anywhere in the world.
C. The SaaS application would be available through any web browser that has an internet connection.
D. The SaaS application would provide on-demand and scalable networking and storage resources.
Show Answer
Correct Answer: C
Explanation:
SaaS delivers fully managed software over the internet, typically accessed through a web browser, making it platform-independent for end users. Option A describes elastic compute resources (IaaS), B describes virtual desktops/DaaS or VDI, and D describes scalable infrastructure resources such as networking and storage (IaaS).

Question 58

A project team is unclear on product deliverables. The project manager proposes gaining the feedback of subject matter experts and other interested stakeholders. Which of the following will best help the project manager better define the product deliverables?

A. Focus groups
B. Tasksetting
C. Workshop
D. Brainstorming
Show Answer
Correct Answer: C
Explanation:
Workshops are a facilitated technique used to bring subject matter experts and key stakeholders together to define and refine requirements, scope, and product deliverables. Focus groups are primarily used to gather perceptions and feedback from selected participants about a product or concept, while brainstorming is for idea generation rather than structured definition of deliverables. 'Tasksetting' is not a standard PMBOK elicitation technique.

Question 59

The project manager notices that the contractor has not been attending the weekly project progress meetings. Which of the following actions should the project manager take?

A. Contact the contractor directly.
B. Cancel the contract.
C. Enforce contract rules of engagement.
D. Issue a contract change notice.
Show Answer
Correct Answer: C
Explanation:
The appropriate first action is to enforce the contractual rules of engagement. Contractor participation in required meetings is typically governed by the contract or communications provisions. The project manager should manage the contractor according to the contract rather than immediately cancel the contract, issue a change notice, or bypass the agreed governance by simply contacting them informally as the primary response.

Question 60

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A. Hold the project until the devices are delivered.
B. Evaluate the impact to baselines.
C. Request another supplier to ship devices.
D. Update the project timeline with a new project end date.
Show Answer
Correct Answer: B
Explanation:
The first action is to assess how the supplier delay affects the project's approved baselines, especially the schedule, but also potentially cost and scope. Only after performing impact analysis should the project manager determine appropriate responses such as seeking an alternate supplier, requesting changes, or updating the schedule. Immediately halting the project or revising the timeline would be premature.

$19

Get all 383 questions with detailed answers and explanations

  • Instant download HTML + PDF delivered the moment payment clears.
  • Secure Stripe checkout we never see or store your card details.
  • 7-day refund if files are defective see our refund policy.