A member keeps bringing up unrelated topics during a team meeting. Which of the following should the project manager do to keep the discussion on track?
A. Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting’s agenda.
B. Ask the team member to leave the meeting and create a new meeting to discuss these topics.
C. Adjust the current meeting’s agenda to accommodate the team member’s topics.
D. Allow the team member to bring up the topics, which could lead to important discussions and insights.
Show Answer
Correct Answer: A
Explanation: The project manager should facilitate effective meetings by keeping discussions aligned with the agenda while ensuring off-topic issues are not dismissed. Reminding the team member of the agenda and suggesting the topic be added to a future meeting (or a parking lot for later discussion) maintains focus, respects the contributor, and supports efficient use of meeting time. The other options either unnecessarily exclude the participant, derail the current meeting, or encourage scope drift.
Question 96
During an active project, the finished product is not meeting quality specifications. Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
A. Communicate the change status.
B. Document change recommendations.
C. Create a change request.
D. Implement the changes.
Show Answer
Correct Answer: C
Explanation: If the product does not meet quality specifications and the project manager has already determined what is needed to resolve the issue, the next step in integrated change control is to formally create a change request. The change must be reviewed and approved before implementation. Documenting recommendations may support the request, communicating status occurs later, and implementing changes should only happen after approval.
Question 97
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
A. Lead architect
B. Project sponsor
C. Program manager
D. Scrum master
Show Answer
Correct Answer: B
Explanation: The project charter is authorized by the project sponsor, who works with the project manager to define the project's objectives, high-level requirements, measurable success criteria, and overall business justification. The lead architect provides technical input, a program manager oversees related projects, and a Scrum master facilitates agile team processes rather than defining charter success criteria.
Question 98
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
A. Remove the team member’s access.
B. Release the project resources.
C. Collect the stakeholders’ feedback.
D. Have the closeout report approved.
Show Answer
Correct Answer: B
Explanation: At project closure, the project manager should formally release project resources so team members can be reassigned and charge time to new work. If a team member is still charging time to a completed project months later, the resource release process was neglected. Removing access is not the primary project management closure responsibility, and stakeholder feedback or closeout report approval do not address resource assignment.
Question 99
Which of the following contract types in project procurement has the highest risk for the buyer?
A. Time and material
B. Cost-plus
C. Fixed-price
D. Unit price
Show Answer
Correct Answer: B
Explanation: Cost-plus contracts place the greatest cost risk on the buyer because the buyer reimburses the seller's allowable costs and typically pays an additional fee. Fixed-price contracts shift more risk to the seller, while time and material and unit price contracts generally allocate risk between the parties depending on scope and usage.
Question 100
Which of the following is a reason to use a SOW on a project?
A. To find out the contact information for the vendors
B. To review the list of stakeholders
C. To ensure the team stays within the scope of the contract
D. To give explicit instruction on how to execute the work
Show Answer
Correct Answer: C
Explanation: A Statement of Work (SOW) defines the project scope, deliverables, responsibilities, and contractual expectations. It is used to ensure the work performed remains within the agreed contractual scope. It is not primarily for vendor contact information, stakeholder lists, or detailed execution instructions.
Question 101
A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes. Which of the following should the company use?
A. Run charts
B. Fishbone/Ishikawa diagrams
C. Scatter plot
D. Decision tree
Show Answer
Correct Answer: B
Explanation: Fishbone (Ishikawa) diagrams are specifically designed for root cause analysis. They help categorize and systematically identify potential causes of defects or quality problems, making them the appropriate tool for investigating and improving manufacturing processes. Run charts show trends over time, scatter plots examine relationships between variables, and decision trees support decision-making rather than root cause analysis.
Question 102
During the project execution, the sponsor would like to have a visual representation indicating the progress of the project. The project is being managed using agile methodologies. Which of the following tools would best help the sponsor with the request?
A. Milestone chart
B. Velocity chart
C. Task board
D. Burndown chart
Show Answer
Correct Answer: D
Explanation: A burndown chart is the standard Agile information radiator that visually shows remaining work against time, allowing stakeholders such as the sponsor to quickly assess project or sprint progress. A milestone chart is more common in predictive projects, a velocity chart shows team throughput rather than overall progress, and a task board shows workflow status but not overall progress over time.
Question 103
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
A. Task log
B. Cadence
C. Milestones
D. Work breakdown structure
Show Answer
Correct Answer: B
Explanation: A repeatable, consistent schedule for iterations, events, tasks, and deliverables is established through cadence. In Agile, cadence is the regular rhythm of sprints and associated activities, creating predictable flow. A task log tracks work, milestones mark key points in time, and a work breakdown structure decomposes scope but does not define a repeating iteration schedule.
Question 104
Which of the following demonstrates awareness of regulations and standards when conducting a project?
A. Establishing a measurement system for the team members’ performance
B. Controlling project costs to fall within the company-approved variance
C. Reviewing advertising trends in the market before launching a new product
D. Submitting architectural plans for approval before commencing construction
Show Answer
Correct Answer: D
Explanation: Awareness of regulations and standards involves complying with applicable legal, regulatory, and industry requirements. Submitting architectural plans for approval before construction demonstrates compliance with building codes and permitting processes. The other options relate to performance management, cost control, or market research rather than regulatory compliance.
$19
Get all 387 questions with detailed answers and explanations
Instant download HTML + PDF delivered the moment payment clears.
Secure Stripe checkout we never see or store your card details.
7-day refund if files are defective see our refund policy.