Question 191

A project manager is working with a new team to review a requirement for a new project. The project manager wants to create artifacts that include roles and responsibilities. Which of the following artifact types best matches these requirements?

A. RACI chart
B. Gantt chart
C. Burndown chart
D. Organizational chart
Show Answer
Correct Answer: A
Explanation:
A RACI chart is specifically designed to document and communicate project roles and responsibilities by identifying who is Responsible, Accountable, Consulted, and Informed for each task or deliverable. A Gantt chart shows schedule, a burndown chart tracks remaining work, and an organizational chart shows reporting structure rather than task responsibilities.

Question 192

Because milestones were not being met, a project manager decided to add more developers to the crucial tasks to help expedite the completion of deliverables. However, the developers’ performance did not improve. Which of the following team life cycles should the project manager move to next?

A. Forming
B. Norming
C. Storming
D. Adjourning
Show Answer
Correct Answer: C
Explanation:
Adding new developers changes team dynamics. Teams typically return to the Forming stage when membership changes, and the next stage in Tuckman's model is Storming, where members adjust, roles are clarified, and conflicts are worked through. Since the question asks which life-cycle stage to move to next, the correct choice is Storming.

Question 193

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

A. RFP
B. RFQ
C. RFB
D. RFI
Show Answer
Correct Answer: A
Explanation:
An RFP (Request for Proposal) is used when an organization has specific business needs and asks vendors to propose a complete solution, including approach, technical details, and pricing. An RFQ is primarily for obtaining price quotes for well-defined products or services, an RFI is for gathering preliminary information when requirements are not yet fully defined, and RFB is used for straightforward competitive bids where the solution is already specified.

Question 194

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

A. Performance testing
B. User acceptance testing
C. Stress testing
D. Unit testing
Show Answer
Correct Answer: B
Explanation:
The issue described is best addressed by regression testing, which verifies that new changes have not broken existing functionality. Because regression testing is not listed, the closest testing cycle among the options is User Acceptance Testing (UAT), which validates that the complete system, including existing and new capabilities, works as expected before release. Performance and stress testing focus on load characteristics, and unit testing verifies individual components rather than end-to-end behavior after deployment.

Question 195

Which of the following is an activity related to operational security?

A. Processing background screening
B. Setting up a firewall
C. Establishing a zone of trust
D. Implementing multifactor authentication
Show Answer
Correct Answer: A
Explanation:
Operational security includes administrative and personnel security activities such as background screening and onboarding processes. The other options are primarily technical or network security controls: firewalls, trust zones, and multifactor authentication.

Question 196

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement. Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

A. Risk register
B. Change log
C. Traceability matrix
D. Project status report
Show Answer
Correct Answer: C
Explanation:
A requirements traceability matrix maps each requirement to corresponding deliverables, verification activities, and status, allowing stakeholders to see both requirements coverage and progress. A risk register tracks risks, a change log tracks changes, and a project status report summarizes overall project status but does not provide detailed requirement-to-deliverable traceability.

Question 197

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

A. Forcing
B. Avoiding
C. Compromising
D. Smoothing
Show Answer
Correct Answer: A
Explanation:
The project manager makes a unilateral decision to continue with the existing process and explicitly does not allow changes after the team failed to reach agreement. This is the forcing (directing) conflict resolution technique, where authority is used to impose a decision. Avoiding would mean postponing or sidestepping the issue rather than making and enforcing a decision.

Question 198

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Choose two.)

A. Purchase the materials.
B. Assign the resources.
C. Accept delays in the work.
D. Approve the deliverables.
E. Monitor the performance.
F. Negotiate with the vendors.
Show Answer
Correct Answer: D, E
Explanation:
When work is outsourced, the project manager remains responsible for vendor oversight and project acceptance. Monitoring the contractor's performance ensures the work stays on schedule, within scope, and meets quality expectations. The project manager also reviews and approves the completed deliverables before formal acceptance. Purchasing materials and assigning resources are typically the vendor's responsibility under the outsourcing agreement. Delays should not simply be accepted, and vendor negotiation is generally part of procurement/contract management rather than the primary responsibility indicated by this scenario.

Question 199

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the BEST chart to use?

A. Milestone
B. Gantt
C. Burndown
D. PERT
Show Answer
Correct Answer: A
Explanation:
A milestone chart is specifically designed to communicate major accomplishments and key events at a high level, making it ideal for a monthly status report. A Gantt chart focuses on the full project schedule and tasks, a burndown chart tracks remaining work over time (typically Agile), and a PERT chart illustrates task dependencies and sequencing.

Question 200

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

A. Status report
B. Issue log
C. Risk report
D. Risk register
Show Answer
Correct Answer: C
Explanation:
The concern about solar flares is a potential future event, so it is a risk rather than an issue. A risk register is the internal repository for identifying and tracking risks, while a risk report is the communication artifact used to summarize risk status and exposure for stakeholders. Since the question asks for the best tool to communicate this information to stakeholders, the risk report is the correct choice.

$19

Get all 383 questions with detailed answers and explanations

  • Instant download HTML + PDF delivered the moment payment clears.
  • Secure Stripe checkout we never see or store your card details.
  • 7-day refund if files are defective see our refund policy.