Question 202

HOTSPOT - A distribution company uses Dynamics 365 Supply Chain Management. A high-volume warehouse for the distribution company automatically releases transfer order lines to the warehouse throughout the day. Order line quantities are frequently changed after release to the warehouse. However, the load lines are not always updated. You need to configure automatic updates to the load lines. What should you configure? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Illustration for MB-330 question 202
Show Answer
Correct Answer: Configure Warehouse parameters. Enable automatic wave creation.
Explanation:
Automatic shipment/load updates for changed transfer order quantities are configured in Warehouse management parameters (auto-update shipment). The wave template should have automatic wave creation enabled so released transfer orders are processed automatically.

Question 203

HOTSPOT - A company uses Dynamics 365 Supply Chain Management. The company uses a Business Unit financial dimension. The dimension is required on items and posted on transactions. The company wants to update item costs but exclude the required financial dimension. The change must include a warning to users before the update. The costing method should be calculated based on the expected, calculated cost to produce an item. You must configure the system to meet the requirements. Which actions should you perform? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Illustration for MB-330 question 203
Show Answer
Correct Answer: Enable: Options of defaulting financial dimensions for inventory standard cost revaluation. Configure: Posting.
Explanation:
The feature allows control over the source of financial dimensions during standard cost revaluation. Setting the origin to Posting excludes required default financial dimensions from the item while warning users before update, and supports standard cost updates based on calculated production cost.

Question 204

A company uses Dynamics 365 Supply Chain Management. The company provides warehouse workers with handheld devices to perform inventory operations. Periodic inventory audits are required due to the frequent theft of some inventory items from a warehouse. Some inventory has been fully depleted. On-hand inventory quantities of other items are consistently incorrect. You need to configure the system to automatically create cycle-counting work. Which two methods can you use? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.

A. threshold parameters
B. work pool
C. cycle count plan
D. work policies
E. inventory journals
Show Answer
Correct Answer: A, C
Explanation:
Dynamics 365 Supply Chain Management supports automatic recurring creation of cycle counting work through either cycle counting thresholds (which trigger counts based on inventory depletion/threshold conditions) or cycle counting plans (scheduled counting based on defined plans). Work pools and work policies do not create cycle-counting work automatically, and inventory journals are used to record adjustments rather than generate warehouse work.

Question 205

A company uses Dynamics 365 Supply Chain Management. The company implements master planning. The company reports delays in the supply chain that have resulted in late deliveries for products. You must simulate several broad delays across all products in the supply chain when calculating lead times. Daily planning for items must not be impacted. You need to configure the system. What should you configure?

A. Planned orders
B. Receipt margins
C. Master plans
D. Coverage groups
E. Released products
Show Answer
Correct Answer: C
Explanation:
Configure receipt margins at the master plan level. Master plan safety margins are intended to simulate longer lead times or uncertainty for a specific planning run without affecting the normal daily planning process. Using a separate master plan allows broad delay simulation across all products while leaving daily planning unchanged. Sources: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/safety-margins

Question 206

A caulking manufacturer is implementing Dynamics 365 Supply Chain Management. When caulking is produced, it is sold by tubes, 1-gallon cans, 5-gallon buckets, 55-gallon drums, or 330-gallon totes with potential to add other sizes. The manufacturer wants to ensure that when new units are added, only one conversion is set up that does not require conversions between each unit of measure. You need to configure the unit of measure to meet the requirement. What should you use?

A. Unit class
B. Conversion formula
C. Formula layout
D. Base unit
Show Answer
Correct Answer: D
Explanation:
Use a base unit within the unit class. By designating one unit as the base unit, you only define a conversion between each unit and the base unit. Dynamics 365 can derive conversions between all other units in the same unit class, so when a new package size is added, only one new conversion is required. Sources: https://www.p2pexams.com/free-questions/microsoft-mb-330-dumps-by-huffman-22-07-2024-7qa-braindumpscollection.pdf

Question 207

HOTSPOT - A company is implementing Dynamics 365 Supply Chain Management. The company uses subcontracted services on its bills of material (BOMs). You must set up and release a subcontractor item so that it can be included on the BOM and subcontractor charges are included in the BOM calculation. Because the subcontractor is a step included in a BOM but not a tangible item, inventory for the item must not be tracked in the warehouse. You need to set up the subcontractor item and release the item to the company. What should you configure? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Illustration for MB-330 question 207
Show Answer
Correct Answer: Create subcontractor item for release: Service product type Set up inventory policy: Select stocked product
Explanation:
Subcontracted operation items are created as Service products. For subcontracting on BOMs/route operations, the service must be configured as a stocked product so it can participate in BOM costing and required inventory transactions, even though it is not a physical warehouse-stocked item with on-hand inventory.

Question 208

HOTSPOT - A distribution company that uses Dynamics 365 Supply Chain Management values inventory through standard cost. The company does not manufacture any products. Some items require incremental updates to the standard cost. The original costs must be retained for reporting purposes. You need to update the standard costs of the items. What should you configure? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Illustration for MB-330 question 208
Show Answer
Correct Answer: Two version None Standard
Explanation:
For standard cost updates in a non-manufacturing environment, use a two-version approach to preserve existing standard costs while preparing new ones. The fallback principle is not needed because it is primarily relevant to cost calculations, especially manufacturing scenarios. The cost type remains Standard.

Question 209

A company uses planning optimization in Dynamics 365 Supply Chain Management. A new item is set up for production with a bill of materials (BOM) and is included in planning optimization. You need to identify the planning output for the item. What are two parts of the output? Each answer represents a partial solution. NOTE: Each correct selection is worth one point.

A. warning
B. production order
C. purchase order
D. action message
Show Answer
Correct Answer: B, D
Explanation:
For an item set up for production with a BOM, planning optimization generates planned production orders to satisfy demand rather than purchase orders. It also produces action messages that recommend changes such as advancing, postponing, or adjusting planned supply based on planning results.

Question 210

A company uses Dynamics 365 Supply Chain Management. A large item fits only one item per pallet. A purchase order for the item must be a minimum of 24. Additional line quantities for the item must be in multiples of 24. An incorrect setup for the item allows entry of multiples of 50. This setup error causes purchase order entry overrides. You must configure the system to enforce a match of default quantities during setup. What should you do?

A. Select the Strict option.
B. Select the Standard option.
C. Configure Warehouse management options.
Show Answer
Correct Answer: A
Explanation:
The correct configuration is to select the Strict validation option in Default order settings. Strict validation enforces that order quantities comply with the configured minimum order quantity and quantity multiple (for example, minimum 24 and multiples of 24), preventing overrides caused by mismatched default quantities. The Standard option allows more flexibility and does not strictly enforce these constraints, while Warehouse management options are unrelated to default order quantity validation.

Question 211

A company is implementing Dynamics 365 Supply Chain Management in one legal entity that contains Site1 and Site2. ItemA is a configured item, with configurations ConfigA and ConfigB. The business decides to stop buying ItemA ConfigB into Site2 but will still buy it at Site1. You must configure ItemA to ensure the buying rules are implemented. What should you configure?

A. Variant group
B. Select product variants to release
C. Variant suggestions
D. Default order setting rules
Show Answer
Correct Answer: D
Explanation:
Use Default order setting rules to control purchasing by site and variant. You can stop purchase orders for a specific item variant (such as ConfigB) at Site2 while still allowing purchases at Site1. The other options do not enforce site-specific purchasing restrictions for an already released configured item.

$19

Get all 416 questions with detailed answers and explanations

  • Instant download HTML + PDF delivered the moment payment clears.
  • Secure Stripe checkout we never see or store your card details.
  • 7-day refund if files are defective see our refund policy.